Infrastructure Projects - Outer Ring Road
  Sanction Wise   Agreement Wise
Click on Number to view the list
Amount in Lacs
Infrastructure Projects - Outer Ring Road
Less than 1 crore 1 crore to 5 crore 5 crore to 25 crore 25 crore to 100 crore More than 100 crore Total
Status Number Amount Number Amount Number Amount Number Amount Number Amount Number Amount
Work in Progress 6 ₹ 334.59 1 ₹ 1932.54 7 ₹ 2267.13
Sanction Work not yet Started 7 ₹ 240.75 7 ₹ 240.75
Work yet to be Sanctioned 2 ₹ 319.57 2 ₹ 319.57
Conceptual Stage / Planning 24 ₹ 479.15 2 ₹ 703.76 1 ₹ 2554.45 27 ₹ 3737.37
Completed in 2025 - 26
Completed in 2024 - 25
Completed before 2024 - 25 190 ₹ 4972.42 19 ₹ 3113.31 7 ₹ 5804.66 1 ₹ 7664316.00 217 ₹ 7678206.40
* Total Amount of Projects